Chandigarh, Feb 23 (IANS) Having suffered a delay of nearly five years due to various factors, the 136-km Kundli-Manesar-Palwal Expressway project may finally be completed with the Haryana government approving resumption of work on the stalled project.
"Chief Minister Manohar Lal Khattar has given his approval for resuming work on the project in two phases. While the Manesar-Palwal section would be completed in nine months, the Manesar-Kundli section would be completed in two years," a spokesman of the Haryana State Industrial and Infrastructural Development Corporation (HSIIDC), which is the executing agency of the project, said here Monday.
The Supreme Court had Jan 30 directed the Haryana government to award the contract for the project to a new concessionaire within two months. The new concessionaire will have to commence work within a month's time, the spokesman said.
The construction work on the six-lane expressway, slated to pass through five districts in Haryana - Sonipat, Jhajjar, Gurgaon, Mewat and Palwal - was stalled following certain issues with the concessionaire which was constructing it.
The project, launched with much fanfare by the previous Congress government led by Bhupinder Singh Hooda, has been delayed much beyond its completion deadline of December 2009.
The crucial project was being executed by M/s KMP Expressways Ltd., a consortium of DSC Ltd. and Apollo Enterprises.
The concessionaire was accused by the Hooda government of missing completion deadlines repeatedly.
The concessionaire alleged that the government had failed to acquire land for the project in time leading to cost escalation. Less than 65 percent of the project had been completed till October 2011.
The Haryana government, after repeated warnings, invoked the penalty clause against the concessionaire which approached the Supreme Court.
The spokesman said completion of the project would not only provide high-speed link to northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal, but also de-congest the National Capital Territory (NCT) of Delhi.
Khattar had earlier made it clear that hindrances coming in the way of construction of the KMP Expressway were being removed and work on the project would start soon.
The KMP expressway will ease the inflow of traffic, especially heavy vehicles like trucks, passing through the national capital.
The significance of the expressway is not only that it will connect four major national highways (NH), NH-1 (Delhi-Ambala-Amritsar), NH-2 (Delhi-Agra-Varanasi-Dankuni), NH-8 (Delhi-Jaipur-Ahmedabad-Mumbai) and NH-10 (Delhi-Hisar-Fazilka-Pakistan border), but will significantly reduce the traffic from north Indian states to central, western and south India and vice versa.
Thousands of vehicles, especially trucks, which now pass through New Delhi, will be able to bypass the national capital once the KMP expressway is completed.
Originally slated to be completed in November 2009, the nearly Rs.19 billion (Rs.1,900 crore) expressway missed several deadlines.
Gujarat Election 2022: Hardik Patel's target on Congress, asked why so much hatred for Hindus?
Politician and social worker Hardik Patel, who gave a big blow to the Congress ahead of the upcoming assembly elections in Gujarat, has now made serious allegations against the Congress. Recently,
IND vs SL Playing 11: India will look to make a comeback against Sri Lanka, Riyan Parag may get a chance in place of Dubey
When the Indian team plays the third ODI against Sri Lanka on Wednesday, it will try to forget the previous defeat and make a comeback. India has not lost any ODI series against Sri Lanka for 27 years
Putin is doing what Hitler did: Soldiers statue with rifles deployed in Russia, 'soldiers' will distribute Christmas gifts instead of Santa
Russia engaged in war with Ukraine is showing warlike passion in every act. Christmas was also no exception to this. This time in many cities in Russia, instead of Santa Claus, statues of soldiers
Uber cab driver diverted route with intent of rape: Prosecution
New Delhi, Feb 19 (IANS) Rape-accused Uber taxi driver Shiv Kumar Yadav, instead of taking his woman passenger to her destination, diverted the route with the intention to commit rape, the
Goa mining: Ministry lifts stay on green clearances
Panaji, March 21 (IANS) The union ministry for environment and forests (MoEF) has formally lifted its 2012 order holding all environment clearances (EC) granted to Goa's iron ore mines in
Mohammad Zubair gets big relief from Supreme Court, gets interim bail; All cases registered in UP transferred to Delhi
The Supreme Court on Tuesday granted bail to Alt News co-founder and fact-checker Mohammad Zubair in all the six FIRs registered against him in Uttar Pradesh. "There is no justification for continuing
Earthquake in Delhi: Delhi-NCR was shaken by strong tremors of an earthquake early in the morning, people came out of their homes in panic.
Earthquake in Delhi NCR Strong tremors of earthquake were felt in Delhi-NCR. People had not even woken up early in the morning when beds and windows started shaking loudly. Everyone was frightened by
Rebellion in Shiv Sena in the past: Shinde faction was ready to break the party if it did not go with BJP in 2014, Uddhav had to bow down
Eknath Shinde on Thursday released a video of 42 MLAs proving that he is now in command of the real Shiv Sena. After this, it is believed that the MLAs of the Shinde faction can separate from
Nitish Kumar begins 24-hour fast against land acquisition bill
Patna, March 14 (IANS) Bihar Chief Minister Nitish Kumar began a 24-hour fast here on Saturday morning in protest against the land acquisition amendment bill of the Narendra Modi government.His
New police action in Sambhal riot: Now close associates of the accused are on the radar, more than 200 are on target; call details are being scrutinized
People close to the absconding accused of the Sambhal riot are on the police radar. Police are trying to reach the accused through them. Police have obtained CDR of mobile phones of more than 200