Chandigarh, Feb 23 (IANS) Having suffered a delay of nearly five years due to various factors, the 136-km Kundli-Manesar-Palwal Expressway project may finally be completed with the Haryana government approving resumption of work on the stalled project.
"Chief Minister Manohar Lal Khattar has given his approval for resuming work on the project in two phases. While the Manesar-Palwal section would be completed in nine months, the Manesar-Kundli section would be completed in two years," a spokesman of the Haryana State Industrial and Infrastructural Development Corporation (HSIIDC), which is the executing agency of the project, said here Monday.
The Supreme Court had Jan 30 directed the Haryana government to award the contract for the project to a new concessionaire within two months. The new concessionaire will have to commence work within a month's time, the spokesman said.
The construction work on the six-lane expressway, slated to pass through five districts in Haryana - Sonipat, Jhajjar, Gurgaon, Mewat and Palwal - was stalled following certain issues with the concessionaire which was constructing it.
The project, launched with much fanfare by the previous Congress government led by Bhupinder Singh Hooda, has been delayed much beyond its completion deadline of December 2009.
The crucial project was being executed by M/s KMP Expressways Ltd., a consortium of DSC Ltd. and Apollo Enterprises.
The concessionaire was accused by the Hooda government of missing completion deadlines repeatedly.
The concessionaire alleged that the government had failed to acquire land for the project in time leading to cost escalation. Less than 65 percent of the project had been completed till October 2011.
The Haryana government, after repeated warnings, invoked the penalty clause against the concessionaire which approached the Supreme Court.
The spokesman said completion of the project would not only provide high-speed link to northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal, but also de-congest the National Capital Territory (NCT) of Delhi.
Khattar had earlier made it clear that hindrances coming in the way of construction of the KMP Expressway were being removed and work on the project would start soon.
The KMP expressway will ease the inflow of traffic, especially heavy vehicles like trucks, passing through the national capital.
The significance of the expressway is not only that it will connect four major national highways (NH), NH-1 (Delhi-Ambala-Amritsar), NH-2 (Delhi-Agra-Varanasi-Dankuni), NH-8 (Delhi-Jaipur-Ahmedabad-Mumbai) and NH-10 (Delhi-Hisar-Fazilka-Pakistan border), but will significantly reduce the traffic from north Indian states to central, western and south India and vice versa.
Thousands of vehicles, especially trucks, which now pass through New Delhi, will be able to bypass the national capital once the KMP expressway is completed.
Originally slated to be completed in November 2009, the nearly Rs.19 billion (Rs.1,900 crore) expressway missed several deadlines.
First day: aircraft flew after 60 days, many flights also canceled, passengers looked frustrated and upset
Domestic airlines that had been shut down for nearly two months were restored today due to the lockdown implemented to deal with the Corona virus. After this, hundreds of people started arriving at
Pakistan's PM-ministers will not take salary: Shahbaz Sharif said- Pay the bills of electricity, water and gas yourself; silence on the mighty army
With foreign reserves (deposits) of only $ 3 billion, the last attempt to save Pakistan, which is on the verge of bankruptcy, has begun. Prime Minister Shahbaz Sharif made important announcements
Ram Mandir: 'Whether any party is involved or not, I will go..., Harbhajan's statement on attending Pran Pratistha
Former Indian cricketer and Rajya Sabha MP Harbhajan Singh has said that the upcoming consecration ceremony of the Ram temple in Ayodhya will be an important occasion. He urged people to participate
IPL 2022: This may be Kolkata's playing XI in front of Hyderabad, these two players can get a chance
In front of the Hyderabad team, Kolkata will try to rectify the mistakes made in the previous match. Aaron Finch may make a comeback in this match which means Ajinkya Rahane may have to sit out. Runs
All countries alert regarding Coronavirus, China told citizens - will achieve 'final victory'
The coronavirus is causing havoc in China on a large scale. Governments all over the world have become alert after the outbreak of Covid-19. Amid global concerns over the virus, the Chinese government
Maharashtra: Uddhav resigns from the post of CM without facing the House, Fadnavis can claim to form government today
Maharashtra Chief Minister Uddhav Thackeray, who was reduced to a minority by the rebellion of Shiv Sena MLAs, resigned on Wednesday night. Governor Bhagat Singh Koshyari had instructed Thackeray late
51,552 people attend India-Bangladesh match
Melbourne, March 19 (IANS) As many as 51,552 people thronged the Melbourne Cricket Ground (MCG) here to watch India beat Bangladesh in the cricket World Cup quarter-final on
Weather Update: Temperature may reach 46 degrees Celsius in Delhi today, alert issued in these states, know the condition of your state
This time all over North India including Delhi NCR is getting record-breaking heat. The mercury has reached above 44 in the capital. Hot winds are making life difficult for people during the day. The
Great discomfort in Bangladesh and Brazil for vaccine made in India
After the approval of the emergency use of two vaccines for the Coronavirus in India, countries like Bangladesh and Brazil are looking towards India with hopeful eyes.
Fury performance in Karnal against Sonali Phogat
Market committee employees today protested against Tic Tac Star and BJP leader Sonali Phogat. Employees of the Market Committee organized a demonstration in the premises of Karnal in protest against