New Delhi, Jan 30 (IANS) The Supreme Court Friday asked the Haryana government to award fresh contracts for the construction of Eastern and Western peripheral express corridor around Delhi within two months and giving another month's time to new contractors to commence work.
Taking a strong exception to inordinate delay in the completion of Eastern and Western peripheral express corridors, the green bench of Chief Justice H.L.Dattu, Justice Arun Mishra and Justice Adarsh Kumar Goel said that a project which was ordered 10 years back was far from over.
The court said that the pace at which work was proceeding, it would another two decades for the two corridors to complete. "We started in 2005, 10 years ago, at this pace it will take another two decades," it observed.
The court, taking note of Haryana government's fresh affidavit which said that "though it is said that 65 percent of work is complete but in fact nothing has been done", asked: "Where were your engineers" and for "doing nothing you are willing to pay them Rs.1,300 crores".
The two corridors are being constructed to divert the heavy traffic which is at present using national capital as a transit to go to Uttar Pradesh, Punjab, and Uttrakhand. The project was mooted in the wake of alarmingly rising air pollution in Delhi.
As the court was told that there were legal wrangles on account of payment of the old contractor whose contract has been terminated, it said: "We are concerned with the work. Whether A does it, B does it or C does it."
Directing two months for the award of the contract and another month for the commencement of work, the court said that things don't change with the change of the government.
As Haryana said that it would require six months time for completing the award of contract and the commencement of work as it has also to settle financial aspects with the earlier contractor, the court asked the state government to squeeze its time schedule.
The court said that its direction on the award of contracts to new contractors would not come in the way of the arbitration proceedings on the payment of Rs.1,300 crore to the earlier contractor for the work already done.
Senior counsel Kapil Sibal who appeared for the contractor whose contract has been terminated said that the order of the court awarding fresh contracts would come in the way of arbitration proceedings.
Unmoved and unwilling to retract its position, the court said: "Mr.Sibal, people are suffering. We have to go ahead."
National Herald Case: Rahul Gandhi to appear before ED on June 13, Congress made this special plan
Congress on ED Notice to Sonia and Rahul Gandhi: In the National Herald case, Congress interim pr
In the first Test match played between Sri Lanka and New Zealand (SL vs NZ 1st Test), New Zealand
On Monday morning, lakhs of youth took to the streets in Nepal. The anger of the youth was sparke
Vivo S2 India Launch Date Confirmed: Premium Design, Powerful Camera Smartphone Arrives Soon
Vivo has officially confirmed the India launch date of its upcoming Vivo S2 smartphone. The premi
Case of calling student Kasab: Karnataka Education Minister said, we all use these words
MIT Prof Terrorist Remark: On the matter of a Manipal University professor calling a student "Kas
Respect the rule of law, 43 countries showed the mirror to China on Uighur Muslims
The dragon has been reprimanded by 43 countries around the world for atrocities against Uighur Mu
On Tuesday, the number of corona patients in the country crossed 37 lakh. So far 37 lakh 66 thous
Metro services on Holi from 2.30 p.m.
New Delhi, March 4 (IANS) Delhi Metro services on Holi wil
Every day reshuffle is going on in the corona cases in the country. On the last day i.e. on Wedne
SC issues notice to Centre over Mullaperiyar dam's security
New Delhi, Feb 20 (IANS) The Supreme Court Friday issued notice to the Centre seeking its respo