New Delhi, Jan 30 (IANS) The Supreme Court Friday asked the Haryana government to award fresh contracts for the construction of Eastern and Western peripheral express corridor around Delhi within two months and giving another month's time to new contractors to commence work.
Taking a strong exception to inordinate delay in the completion of Eastern and Western peripheral express corridors, the green bench of Chief Justice H.L.Dattu, Justice Arun Mishra and Justice Adarsh Kumar Goel said that a project which was ordered 10 years back was far from over.
The court said that the pace at which work was proceeding, it would another two decades for the two corridors to complete. "We started in 2005, 10 years ago, at this pace it will take another two decades," it observed.
The court, taking note of Haryana government's fresh affidavit which said that "though it is said that 65 percent of work is complete but in fact nothing has been done", asked: "Where were your engineers" and for "doing nothing you are willing to pay them Rs.1,300 crores".
The two corridors are being constructed to divert the heavy traffic which is at present using national capital as a transit to go to Uttar Pradesh, Punjab, and Uttrakhand. The project was mooted in the wake of alarmingly rising air pollution in Delhi.
As the court was told that there were legal wrangles on account of payment of the old contractor whose contract has been terminated, it said: "We are concerned with the work. Whether A does it, B does it or C does it."
Directing two months for the award of the contract and another month for the commencement of work, the court said that things don't change with the change of the government.
As Haryana said that it would require six months time for completing the award of contract and the commencement of work as it has also to settle financial aspects with the earlier contractor, the court asked the state government to squeeze its time schedule.
The court said that its direction on the award of contracts to new contractors would not come in the way of the arbitration proceedings on the payment of Rs.1,300 crore to the earlier contractor for the work already done.
Senior counsel Kapil Sibal who appeared for the contractor whose contract has been terminated said that the order of the court awarding fresh contracts would come in the way of arbitration proceedings.
Unmoved and unwilling to retract its position, the court said: "Mr.Sibal, people are suffering. We have to go ahead."
The last league match of the IPL 2022 season was played between Sunrisers Hyderabad and Punjab Ki
IT Sector Hiring: Relief news for IT professionals, companies preparing to recruit 3.6 lakhs
There is big news for IT professionals, according to a report, 3.6 lakh recruitments will be done
NDA candidate Draupadi Murmu and the opposition's joint candidate Yashwant Sinha are in the race
New Delhi: As the investigation of the crime branch in Nizamuddin's Tabligi Jamaat case is procee
Maharashtra to scrap Local Body Tax
Mumbai, March 18 (IANS) Maharashtra Finance Minister Sudhir Mungantiwar on Wednesday announced
Samsung Vice Chairman JY Lee jailed for two and a half years, know what is the whole matter
A South Korean court sentenced JY Lee, vice chairman of Samsung Electronics, to two and a half ye
Kolkata school children to get glimpse of Japan
Kolkata, Feb 10 (IANS) The Japanese consulate here will display audio-visuals of the nation's t
India, Bahrain to start talks on defence cooperation
New Delhi, Feb 23 (IANS) India and key Gulf partner Bahrain have agreed to start negotiations o
Giving a big gift to the central employees of the Narendra Modi government in the past, the DA re
There has been a lapse in the security of Union Home Minister Amit Shah. The TRS leader parked hi