Haryana to resume work on stuck KMP expressway


Posted on 24th Feb 2015 12:34 pm by mohit kumar

Chandigarh, Feb 23 (IANS) Having suffered a delay of nearly five years due to various factors, the 136-km Kundli-Manesar-Palwal Expressway project may finally be completed with the Haryana government approving resumption of work on the stalled project.

"Chief Minister Manohar Lal Khattar has given his approval for resuming work on the project in two phases. While the Manesar-Palwal section would be completed in nine months, the Manesar-Kundli section would be completed in two years," a spokesman of the Haryana State Industrial and Infrastructural Development Corporation (HSIIDC), which is the executing agency of the project, said here Monday.

The Supreme Court had Jan 30 directed the Haryana government to award the contract for the project to a new concessionaire within two months. The new concessionaire will have to commence work within a month's time, the spokesman said.

The construction work on the six-lane expressway, slated to pass through five districts in Haryana - Sonipat, Jhajjar, Gurgaon, Mewat and Palwal - was stalled following certain issues with the concessionaire which was constructing it.

The project, launched with much fanfare by the previous Congress government led by Bhupinder Singh Hooda, has been delayed much beyond its completion deadline of December 2009.

The crucial project was being executed by M/s KMP Expressways Ltd., a consortium of DSC Ltd. and Apollo Enterprises.

The concessionaire was accused by the Hooda government of missing completion deadlines repeatedly.

The concessionaire alleged that the government had failed to acquire land for the project in time leading to cost escalation. Less than 65 percent of the project had been completed till October 2011.

The Haryana government, after repeated warnings, invoked the penalty clause against the concessionaire which approached the Supreme Court.

The spokesman said completion of the project would not only provide high-speed link to northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal, but also de-congest the National Capital Territory (NCT) of Delhi.

Khattar had earlier made it clear that hindrances coming in the way of construction of the KMP Expressway were being removed and work on the project would start soon.

The KMP expressway will ease the inflow of traffic, especially heavy vehicles like trucks, passing through the national capital.

The significance of the expressway is not only that it will connect four major national highways (NH), NH-1 (Delhi-Ambala-Amritsar), NH-2 (Delhi-Agra-Varanasi-Dankuni), NH-8 (Delhi-Jaipur-Ahmedabad-Mumbai) and NH-10 (Delhi-Hisar-Fazilka-Pakistan border), but will significantly reduce the traffic from north Indian states to central, western and south India and vice versa.

Thousands of vehicles, especially trucks, which now pass through New Delhi, will be able to bypass the national capital once the KMP expressway is completed.

Originally slated to be completed in November 2009, the nearly Rs.19 billion (Rs.1,900 crore) expressway missed several deadlines.

Did you know?Explore Trending and Topic pages for more stories like this.
0 Like 0 Dislike
Previous news Next news
Other news

Google I/O 2026 Tonight: 5 Big Announcements Sundar Pichai Could Reveal From AI to Android 17

The wait is finally over as Google I/O 2026, Google’s biggest annual developer conference,

Ukraine crisis: what is NATO and why doesn't Russia trust it?

Russia's invasion of Ukraine posed the biggest challenge to NATO in its 73-year history.

Shimla Masjid Dispute Row: 'Outsiders are a threat to Himachal', Kangana Ranaut's statement on the mosque dispute; gave a piece of her mind to the government

Actress and BJP MP from Mandi parliamentary constituency Kangana Ranaut said that using fake

Terrorists are using hi-tech technology in Jammu and Kashmir, to help in avoiding siege by security forces

Jammu Kashmir Terror News: During the last week, terrorists managed to escape the siege of securi

50 illegal colonies made by cutting a plot in Gurugram in one and a half months, revealed in the survey of the district town planner

Even after strict enforcement of Gurugram District Town Planner, land mafia cutting illegal colon

Oscar Awards 2024: This brother-sister pair did wonders by winning the Oscar at the youngest age, breaking this 87-year-old record

Oscar Awards 2024: Everyone's eyes are on the Oscar Awards, one of the most important awards in t

World Mental Health Day 2022: When and why is 'World Mental Health Day celebrated? Know what is the theme of this time

World Mental Health Day is celebrated every year on 10 October. It was started in 1992 at the ini

'If I get a chance, I will destroy Pakistan, ' Colonel Sofia's father fought in the Bangladesh war, said this on Operation Sindoor.

India has avenged the terrorist attack in Pahalgam by carrying out air strikes at 9 places in Pak

West Bengal elections: BJP is focusing on these communities, quietly engaged in changing the electoral picture

In West Bengal, the elections are going to be held in 8 phases, all the parties are eyeing the Mu

Indonesia Oil Depot Fire: Fierce fire in oil depot in Indonesia, 17 killed; evacuation of thousands

A massive fire broke out at a fuel storage depot in the Indonesian capital on Friday, killing at

Sign up to write
Sign up now if you have flare of writing..
Login   |   Register
Follow Us
Indyaspeak @ Facebook Indyaspeak @ Twitter Indyaspeak @ Pinterest RSS



Play Free Quiz and Win Cash