Haryana to resume work on stuck KMP expressway


Posted on 24th Feb 2015 12:34 pm by mohit kumar

Chandigarh, Feb 23 (IANS) Having suffered a delay of nearly five years due to various factors, the 136-km Kundli-Manesar-Palwal Expressway project may finally be completed with the Haryana government approving resumption of work on the stalled project.

"Chief Minister Manohar Lal Khattar has given his approval for resuming work on the project in two phases. While the Manesar-Palwal section would be completed in nine months, the Manesar-Kundli section would be completed in two years," a spokesman of the Haryana State Industrial and Infrastructural Development Corporation (HSIIDC), which is the executing agency of the project, said here Monday.

The Supreme Court had Jan 30 directed the Haryana government to award the contract for the project to a new concessionaire within two months. The new concessionaire will have to commence work within a month's time, the spokesman said.

The construction work on the six-lane expressway, slated to pass through five districts in Haryana - Sonipat, Jhajjar, Gurgaon, Mewat and Palwal - was stalled following certain issues with the concessionaire which was constructing it.

The project, launched with much fanfare by the previous Congress government led by Bhupinder Singh Hooda, has been delayed much beyond its completion deadline of December 2009.

The crucial project was being executed by M/s KMP Expressways Ltd., a consortium of DSC Ltd. and Apollo Enterprises.

The concessionaire was accused by the Hooda government of missing completion deadlines repeatedly.

The concessionaire alleged that the government had failed to acquire land for the project in time leading to cost escalation. Less than 65 percent of the project had been completed till October 2011.

The Haryana government, after repeated warnings, invoked the penalty clause against the concessionaire which approached the Supreme Court.

The spokesman said completion of the project would not only provide high-speed link to northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal, but also de-congest the National Capital Territory (NCT) of Delhi.

Khattar had earlier made it clear that hindrances coming in the way of construction of the KMP Expressway were being removed and work on the project would start soon.

The KMP expressway will ease the inflow of traffic, especially heavy vehicles like trucks, passing through the national capital.

The significance of the expressway is not only that it will connect four major national highways (NH), NH-1 (Delhi-Ambala-Amritsar), NH-2 (Delhi-Agra-Varanasi-Dankuni), NH-8 (Delhi-Jaipur-Ahmedabad-Mumbai) and NH-10 (Delhi-Hisar-Fazilka-Pakistan border), but will significantly reduce the traffic from north Indian states to central, western and south India and vice versa.

Thousands of vehicles, especially trucks, which now pass through New Delhi, will be able to bypass the national capital once the KMP expressway is completed.

Originally slated to be completed in November 2009, the nearly Rs.19 billion (Rs.1,900 crore) expressway missed several deadlines.

0 Like 0 Dislike
Previous news Next news
Other news

OnePlus 10R and Nord CE 2 Lite price and features leaked, here are the full details

OnePlus Launch: OnePlus is holding an event on April 28 to launch the OnePlus 10R, Nord CE 2 Lite

Jammu Kashmir: Tension after hate speech in Bhaderwah, the administration imposed a curfew

Conspiracies are continuing to create tension in Bhaderwah (Doda) and Kishtwar districts through

IPL: Five Indian players including Suryakumar Yadav, who claim for Team India with great performance

The league round of the 13th season of the Indian Premier League is over. In the league round thi

These 5G smartphones are making a splash in the Indian market, know their price

New Delhi: In today's era, the importance of smartphones has increased a lot. Today, people use s

Don't read Quran on my death, celebrate: The last message of an anti-hijab activist before sentence in Iran, publicly hanged

In Iran, a 23-year-old boy opposing the hijab was publicly hanged. The matter is of December 12,

Gaza's only corona testing lab destroyed in Israeli airstrikes, work closed: report

The Israeli attack also damaged the Corona Virus Testing Lab, the only corona in the Gaza Strip.

India, China hold border talks

New Delhi, March 23 (IANS) National Security Advisor Ajit Doval, the special rRepresentative fo

PM Modi said – India is preparing modern digital infrastructure, and money is directly reaching the account of the poor through JAM

Prime Minister Narendra Modi on Tuesday said India is building a modern digital infrastructure an

Religion should be personal choice: Naidu

New Delhi, Feb 19 (IANS) Clearing the government's position on the controversial 'ghar wapsi' e

Russia-Ukraine War: US General Mark claims – Military task to drive Russia out of Ukraine is very difficult

Countries around the world have criticized Russia after the Russian missile fell in Poland. Ameri

Sign up to write
Sign up now if you have flare of writing..
Login   |   Register
Follow Us
Indyaspeak @ Facebook Indyaspeak @ Twitter Indyaspeak @ Pinterest RSS



Play Free Quiz and Win Cash