Haryana to resume work on stuck KMP expressway


Posted on 24th Feb 2015 12:34 pm by mohit kumar

Chandigarh, Feb 23 (IANS) Having suffered a delay of nearly five years due to various factors, the 136-km Kundli-Manesar-Palwal Expressway project may finally be completed with the Haryana government approving resumption of work on the stalled project.

"Chief Minister Manohar Lal Khattar has given his approval for resuming work on the project in two phases. While the Manesar-Palwal section would be completed in nine months, the Manesar-Kundli section would be completed in two years," a spokesman of the Haryana State Industrial and Infrastructural Development Corporation (HSIIDC), which is the executing agency of the project, said here Monday.

The Supreme Court had Jan 30 directed the Haryana government to award the contract for the project to a new concessionaire within two months. The new concessionaire will have to commence work within a month's time, the spokesman said.

The construction work on the six-lane expressway, slated to pass through five districts in Haryana - Sonipat, Jhajjar, Gurgaon, Mewat and Palwal - was stalled following certain issues with the concessionaire which was constructing it.

The project, launched with much fanfare by the previous Congress government led by Bhupinder Singh Hooda, has been delayed much beyond its completion deadline of December 2009.

The crucial project was being executed by M/s KMP Expressways Ltd., a consortium of DSC Ltd. and Apollo Enterprises.

The concessionaire was accused by the Hooda government of missing completion deadlines repeatedly.

The concessionaire alleged that the government had failed to acquire land for the project in time leading to cost escalation. Less than 65 percent of the project had been completed till October 2011.

The Haryana government, after repeated warnings, invoked the penalty clause against the concessionaire which approached the Supreme Court.

The spokesman said completion of the project would not only provide high-speed link to northern Haryana with its southern districts like Gurgaon, Faridabad and Palwal, but also de-congest the National Capital Territory (NCT) of Delhi.

Khattar had earlier made it clear that hindrances coming in the way of construction of the KMP Expressway were being removed and work on the project would start soon.

The KMP expressway will ease the inflow of traffic, especially heavy vehicles like trucks, passing through the national capital.

The significance of the expressway is not only that it will connect four major national highways (NH), NH-1 (Delhi-Ambala-Amritsar), NH-2 (Delhi-Agra-Varanasi-Dankuni), NH-8 (Delhi-Jaipur-Ahmedabad-Mumbai) and NH-10 (Delhi-Hisar-Fazilka-Pakistan border), but will significantly reduce the traffic from north Indian states to central, western and south India and vice versa.

Thousands of vehicles, especially trucks, which now pass through New Delhi, will be able to bypass the national capital once the KMP expressway is completed.

Originally slated to be completed in November 2009, the nearly Rs.19 billion (Rs.1,900 crore) expressway missed several deadlines.

0 Like 0 Dislike
Previous news Next news
Other news

Despite Ukraine tension, Russia and America are with each other in space, American astronaut will return to Earth in Russian spacecraft

Despite tensions over the Ukraine invasion, cooperation between the United States and Russia cont

Demand for FIR in the case of cash found at judge's house, Supreme Court said - there will be no immediate hearing.

The Supreme Court on Wednesday rejected the request for an immediate hearing on the demand to dir

Covid 19: First plasma therapy successful in the country, corona patient's health is improving

new Delhi. No treatment or vaccine has yet been found for Coronavirus, which is causing havoc in

New START Treaty: Putin suspends START nuclear deal with US, apprehensions about war increased

Warning to Western countries, Russian President Vladimir Putin announced the termination of the N

Putin's threat to the US: Said- We have the world's most dangerous nuclear weapons, yet will not use first

Moscow. Russian President Vladimir Putin has openly threatened America without naming it. Putin s

Heart Attack: Breathing broke out in the blink of an eye: People's lives snatched away in a moment while watching dance...

In the recent past, many people have lost their lives due to heart attacks. Some of these cases w

Haryana to probe Gurgaon ex-chief engineer's assets

Gurgaon, March 27 (IANS) Haryana's vigilance department has ordered a probe into former chief e

China Seeks To Dominate Post-COVID-19 World, But Beijing's Role In Downplaying Pandemic Won't Be Forgotten

1945 में द्वितीय विश्व युद्ध के अंत ने स

Moon was formed in a few hours, not thousands of years: Scientists raised questions on their theory, and new research is done with supercomputer

How the Moon was formed has always been an interesting topic of research for scientists. Since th

Rupee vs Dollar: Indian Rupee is at the lowest level against the Dollar, Bhutanese currency Ngultrum is also stronger than us

With the opening of the market on Wednesday, the Indian rupee has been seen trading at a record l

Sign up to write
Sign up now if you have flare of writing..
Login   |   Register
Follow Us
Indyaspeak @ Facebook Indyaspeak @ Twitter Indyaspeak @ Pinterest RSS



Play Free Quiz and Win Cash